
Works are progressing well at our site in Potters Bar, this month the removal of the top halves and backfill of the decommissioned fuel tanks were completed, allowing us to form the shuttering and steelwork for the base slab.

As works continue at our 33kV cable route in Northampton, our vacuum excavator is proving invaluable as we encounter areas that are heavily congested with services.

Good progress continues at Metroline bus depot in Potters Bar with the excavation and reinstatement of the trench across the length of the concrete yard to install 18no ducts (10 power, 6 comms, 2 lighting) and the installation of new access chambers (1200mm x 1200mm x 1500mm deep) in concrete with D400 lids suitable for carrying the weight of the new buses.

This month we completed the construction of the primary substation build at Graven Hill, Bicester so it can be handed over to the client in readiness for the internal fit out of power, lighting and alarm system.

During May works have progressed well at our major renewable energy project in Norwich.

The construction of the access road to the new Primary Substation at Graven Hill in Bicester has progressed to the laying of the asphalt base and binder along the main stretch of the access road.